Ashoka Ranastalam Anandapuram Road Limited
S.NO | PERTICULAR | DETAILS |
---|---|---|
1 | State | Andhra Pradesh |
2 | Authority | National Highways Authority of India |
3 | Concessionaire | Ashoka Ranastalam Anandapuram Road Limited |
4 | Independent Engineer | MSV International Inc. in association with ARMENGE Engineering and Management |
5 | Project type | HYBRID ANNUITY MODE |
6 | Length of Highway (In Km.) | 47 Km |
7 | Construction Period | 910 Days from Appointed Date |
8 | Concession Period | 910 Days plus 15 years from COD |
9 | Date of Bid | 2nd-Mar-2017 |
10 | Date of LOA | 20th-Mar-2017 |
11 | Date of Signing the Agreement | 2nd-May-2017 |
12 | Appointed Date | 16th-Nov-2017 |